Horizontal Upthrust Constants for a Power Plant

March 8, 2006

 

Horizontal Upthrust Constants For A Power Plant
Horizontal Upthrust Constants for a Power Plant
Horizontal Upthrust Constants For A Power Plant
Multiple Constants During Inspection

The horizontal upthrust constants (Fig. PTP200-U) were fabricated from carbon steel and chrome-moly for a Heat Recovery Steam Generator. The constants range in sizes PTP-200 size 3 to 65 and weigh from 24 lbs to 1,300 lbs. They support loads of 100 lbs to 8,100 lbs. The constants support pipes and equipment subjected to vertical movement due to thermal expansion at locations where transfer of stress to other supports or equipment can be critical. Horizontal upthrust constants are utilized in areas where horizontal travel is unacceptable. Standard testing was completed for performance and quality assurance.

Want to learn more about constant springs? View a constant webinar today!



Access-Our-Webinar-Archives



Read More

March 2006 News

March 4, 2006

Piping Technology & Products, Inc. Performed Field Services for a Power Generating Plant in Texas

PT&P was contracted to assist in the determination of pipe support maintenance at a power plant in Texas. The constant effort support springs with loads of excess of 9,500 lbs and the variable spring supports with loads of 450 lbs were marked for needing attention.

Inspecting Variable Springs For Performance
Cleaning Variable Spring Unit
Inspecting Variable Springs For Performance
Inspecting Variable Springs for Performance

PT&P’s objectives were to:

* Evaluate the pipe supports
* Determine state of performance
* Provide a plan of action
* Train personnel on-site to perform adjustments and replacement of supports or support components
* Provide final inspection of modified supports

After Cleaning &Amp; Preparation Of The Constant
After Cleaning & Preparation of the Constant
Final Assembly With Added Slide Plates
Final Assembly with Added Slide Plates

The pipe supports needing attention could not be set to the required installation position. A plan was initiated to recondition some of the support components such as turnbuckles and rods. This would allow a greater range of field adjustment to the pipe supports. During a planned shut-down, PT&P Field Service Units returned to the site to modify the existing supports. The initial phase of the modifications included bracing the piping in order to isolate and lock the supports in position. Then, they were disconnected from the system and modifications to the assemblies were completed. Afterwards, the supports were reinstalled and any necessary adjustments were completed. A total of eight pipe supports were modified or adjusted.

Roller Bearing Needing Maintenance
Roller Bearing Needing Maintenance
Restored Roller Bearing
Restored Roller Bearing

Do you see a need for a routine inspection of your plant? Contact us for a quote today!